See the 2016 Voter-approved Road Bond Projects
Individual Pre-2016 Projects
FM 110 (East San Marcos Loop) Precinct 1
Project 2 of 2
|
Location
|
South Section: SH 123 to FM 621
Middle Section: FM 621 to SH 80
North Section: SH 80 to Yarrington Road/IH-35
|
Description
Partnership Program
South Section Map
Middle Section Map
North Section Map
|
This project continues the loop east of San Marcos and involves initially constructing two travel lanes (one in each direction) with 10-foot shoulders where no road currently exists for the approximately 11.3-mile corridor and includes an interchange at SH 21 and a railroad overpass at the Union Pacific Railroad tracks. As traffic increases over time, two additional travel lanes and additional interchanges would be constructed. A portion of construction costs will be funded through a Transportation Reinvestment Zone (TRZ) created by the City of San Marcos in partnership with Hays County to capture a portion of the increased value of development occurring along the alignment. Caldwell County will also contribute to the project cost. The County is funding and conducting project development simultaneously for the initial stage of all three sections. TxDOT will let and manage construction of the project. Water line relocations will be included in construction contracts.
In May 2018 the Capital Area Metropolitan Planning Organization (CAMPO) selected the FM 110 project for $30 million in construction funding.
|
Status
|
Environmental
|
Completed
|
ROW Acquisition
|
North-70%, Middle-100%, South 100%
|
Utility Relocation
|
North-28%; Middle-75%, South-90% Waterline relocations will be completed as part of construction.
|
Construction Design
|
90% complete on north and middle segments; 100% on south segment.
|
Estimated Construction Start
|
South Section: SH 123 to FM 621--Spring 2019
Middle Section: FM 621 to SH 80--Spring 2019
North Section: SH 80 to Yarrington Road--Fall 2019
|
FM 110 (East San Marcos Loop) Precinct 1
(Initial Project-Project 1 of 2)
|
Location
|
FM 110 from SH 123 to I-35 at McCarty Lane
|
Description (Completed)
Pass-through Program
|
This project is part of the first segment of the proposed San Marcos Loop east of IH-35 which will connect IH-35 at McCarty Road on the south side of San Marcos to IH-35 at Yarrington Road north of San Marcos. The first phase consisted of the County constructing 1 mile of a 5-lane rural, limited-access roadway to tie into a 1-mile reconstruction (by the City of San Marcos) of existing McCarty Road where a 4-lane urban section was built.
|
Status
|
Open to traffic March 2014
|
CR 266 (Old Bastrop Highway) Precinct 1
|
Location
|
Centerpoint Road (CR 234) to Francis Harris Lane
|
Description (Completed)
2008 Priority Road Bond Program
|
This project widened and reconstructed the Old Bastrop Highway (CR 266) existing roadway to provide for two 12-foot lanes and 10-foot shoulders. Roadway improvements also consisted of realigning Centerpoint Road (CR 234) at Old Bastrop Highway thus eliminating the offset intersection. Safety end treatments were also included through the extension of parallel and cross culverts, replacement of headwalls and installation of guardrail.
|
Status
|
Open to traffic March 2014
|
Funding
|
County Road Bonds: $7.1M
|
Dacy Lane (CR 206) Precincts 1 and 2
|
Location
|
CR 206 from Bebee Road (CR 122) to Windy Hill Road (CR 131) DACY LANE PROJECT INFORMATION WILL BE UPDATED IN OCTOBER 2018. PLEASE CHECK BACK FOR NEW INFORMATION ABOUT THIS IMPORTANT IMPROVEMENT.
|
Description
2008 Priority Road Bond Program
|
This project consists of preliminary engineering required for the development of a design schematic and environmental studies and right of way acquisition to preserve the corridor for the future expansion/realignment of 1.5 miles of Dacy Lane from CR 122 to CR 131. Proposed improvements include a rural section with four 12-foot lanes. A 14-foot left turn lane will be provided at intersections.
|
Status
|
Schematic / Environmental
|
100%
|
ROW Acquisition
|
10%
|
Estimated Construction Start
|
To be determined (Construction not funded in 2008 Priority Road Bond program).
|
Funding
|
County Road Bonds: $1.5M
|
I-35/Yarrington Road Bridge Precincts 1 and 4
|
Description
Pass-through Program
|
This project reconstructed the overpass bridge at Yarrington Road and IH 35 from 0.25 miles north of Yarrington Road to 0.38 miles south of Yarrington Road to address the increasing traffic volume on this segment of Yarrington Road/IH 35. Improvements include realigning and widening segments of the IH 35 frontage road, replacement of the bridge structure at Yarrington Road over IH 35 to accommodate six lanes in the future with sidewalks and construction of turnaround bridges in both directions.
|
Status
|
Construction Start
|
Open to traffic October 2016
|
IH 35 Reversal of Ramps Precincts 1 and 4
|
Location
|
|
Description
Partnership Program
|
This project included reconfiguration of the existing entrance and exit ramps and constructing new ramps as needed to respond to new northbound and southbound access needs along this approximate 5.5-mile section of I-35 from the Blanco River to one-half-mile north of FM 150 (Center Street, Kyle). TxDOT will also develop the schematic design for the widening of I-35 to the Future Transportation Corridor (FTC) typical section including accommodations for the ultimate three (3) frontage road lanes and five (5) main lanes in each direction. Developer participation would be an element of project construction cost-sharing. Project development and construction was funded by TxDOT.
|
Status
|
Construction start April 2016; open to traffic Fall 2017 |
IH 35/Posey Road Interchange Precincts 1 and 3
|
Location
|
Posey Road interchange at IH 35
|
Description
Partnership Program
|
Modifications to the IH 35 and Posey Road intersection are proposed that include removing the existing Posey Road bridge and reconstructing IH 35 over Posey Road, adding frontage road turnarounds at the intersection, two through lanes in each direction at the intersection with Posey Road, and conversion of frontage roads to one-way operation south of Posey Road to York Creek. The project will also consider reversing ramps (changing entrance ramps to exit ramps and exit ramps to entrance ramps) in the following locations:
- SB Entrance ramp between Centerpoint Road and Posey Road
- SB Exit ramp between Centerpoint and Posey Road
- SB Entrance ramp between Posey Road and York Creek Road (FM 1102)
- SB Exit ramp between Posey Road and York Creek Road (FM 1102)
- NB Exit ramp between Posey Road and York Creek Road (FM 1102)
- NB Entrance ramp between Posey Road and York Creek Road (FM 1102)
At the start of the Posey Road Project construction, the frontage roads south of Posey will be converted to one-way traffic operations, southbound only on the west side of I-35 and northbound only on the east side of I-35.
|
Status
|
Environmental
|
Complete
|
ROW Acquisition
|
Complete
|
Utility Relocation
|
90% (waterline & PEC adjustments will be included in construction contract)
|
Construction Design
|
100% Contractor bids opened Aug. 7, 2018
|
Estimated Construction Start
|
Fall 2018
|
IH-35 Phase 2A – FM 150 Realignment Precinct 1
|
Location
|
IH-35 to Lehman Road
|
Description (Completed)
Pass-through Program
|
This project relocated the existing FM 150-IH 35 frontage road intersection and realigned portion of FM 150 east of IH 35 to merge with existing FM 150 East. Upon completion, FM 150 became a continuous facility east and west of IH 35. The City of Kyle contributed $3.0 million to the project.
|
Status
|
Open to traffic October 2013
|
IH-35 Phase 2B Precincts 1 and 2
|
Location
|
FM 150 to FM 1626
|
Description
Pass-through Program
|
This project completed the southbound frontage road system between FM 1626 and RM 150 and included constructing new ramps
|
Status
|
Open to traffic October 2013
|
IH-35 Phase 1 - Kyle Crossing (CR 210) Precinct 2
|
Location
|
CR 210 to FM 1626 (Kyle Parkway)
|
Description (Completed)
Pass-through Program
|
This project reconstructed the substandard 2-lane bridge over IH-35, including a North-South and South-North turn-around bridge. The project also constructed a section of frontage road between Kyle Crossing and FM 1626. Constructing this missing gap of frontage road allowed the IH-35 frontage roads between FM 2001 and FM 1626 to operate as one-way. The City of Kyle, through a State Infrastructure Bank loan, contributed $11 million.
|
Status
|
Open to traffic December 2011
|
IH-35 at FM 2001 Overpass Road Precinct 2
|
Location
|
Wonder World Drive to RM 12/RM 32 Junction
|
Description (Completed)
|
This project improved existing Overpass Road as part of the overall realignment and improvements to FM 2001. Significant improvements to FM 2001 have been made in a partnership between TxDOT, the City of Buda, private developers and Hays County. This is the last connection to the new $20.0 million interchange and frontage road improvements made by TxDOT.
|
Status
|
Open to traffic September 2010
|
FM 2001 (IH-35 to SH 21) Precinct 2
|
Location
|
FM 2001 from IH 35 to SH 21
|
Description
Partnership Program
Map
March 2017 Update
|
This project consists of constructing two travel lanes (one in each direction) and 10-foot shoulders in the interim time frame and construction of two additional travel lanes in the ultimate time frame (to be determined). Some new roadway and some existing right-of-way will be used along the approximate 7.7-mile corridor. The existing Rohde Road/SH 21 intersection will be realigned and a new FM 2001/Rohde Road/SH 21 intersection will be constructed to improve safety. Early project development and right-of-way donation program is being conducted and funded by Hays County with TxDOT funding and managing construction.
|
Status
|
Environmental
|
95%
|
ROW Acquisition
|
20%
|
Utility Relocation
|
0%
|
Construction Design
|
20%
|
Estimated Construction Start
|
To be determined
|
SH 21 at FM 2001 Precinct 2
|
Location
|
At FM 2001 (West) Intersection
|
Description (Completed)
2008 Priority Road Bond Program
|
This project consisted of widening and overlay of the existing SH 21 pavement to add a 14-foot left turn lane and 10-foot shoulders on SH 21 at the intersection with FM 2001 (West).
|
Status
|
Open to traffic: December 2012
|
Funding
|
County Road Bonds: $1.05M
|
SH 21 at High Road (CR 127) Precinct 2
|
Location
|
At High Road (CR 127) Intersection
|
Description (Completed)
2008 Priority Road Bond Program
|
This project consisted of widening and overlay of the existing SH 21 pavement to add a 14-foot left turn lane and 10-foot shoulders on SH 21 at the intersection with High Road (CR 127).
|
Status
|
Open to traffic: December 2010
|
Funding
|
County Road Bonds: $222.3K
|
American Recovery & Reinvestment Act (ARRA) funds: $670K
|
SH 21 at Rhode Road (CR 126) Precinct 2
|
Location
|
At Rhode Road (CR 126) Intersection
|
Description
Originally a 2008 Priority Road Bond Program that was undertaken instead by the County Transportation Dept.
|
This project originally included only safety improvements to Rhode Road at the intersection with SH 21. The County moved forward with additional improvements to Rhode Road beyond the intersection as part of its annual maintenance program. Project was removed from Priority Road Bond Program and work is being done by the County’s Transportation Department.
|
Status
|
Open to traffic: TBD
|
Funding
|
County Road Bonds: $66.5K (Preliminary Planning Prior to Work Performed by County)
|
Robert S. Light Extension/Buda Truck Bypass (IH-35 to FM 1626) Precinct 2
|
Location
|
IH 35 to FM 1626
|
Description
Partnership Program
Map
|
This project consists of constructing two travel lanes (one in each direction) and grade-separated crossing with the Union Pacific Railroad initially and ultimately constructing two additional travel lanes at a later date to be determined. Some new roadway and some existing right-of-way will be used. Project development is being conducted and funded by Hays County with TxDOT funding and managing construction.
|
Status
|
Environmental
|
80%
|
ROW Acquisition
|
25%
|
Utility Relocation
|
25%
|
Construction Design
|
90%
|
Estimated Construction Start
|
Spring 2019
|
Post Road (CR 140) at Blanco River Study Precincts 1 and 4
|
Location
|
At Blanco River Low Water Crossing
|
Description (Study completed)
2008 Priority Road Bond Program
|
This project consisted of a feasibility analysis and preliminary planning study for the replacement of the Low Water Crossing on Post Road over the Blanco River.
|
Status
|
Study completed: February 2010
|
Funding
|
County Road Bonds: $105K
|
RM 967 (FM 1626 to Cole Springs Road) Precinct 2
|
Location
|
RM 967 from FM 1626 to Cole Springs Road
|
Description
Partnership Program
Map
|
This project consisted of constructing a center turn lane and adding shoulders and sidewalks to the existing two-lane roadway. A portion of the approximate 2.6-mile project from FM 1626 to FM 2770 will be removed from the State Highway System and transferred to the City of Buda for operations and maintenance. Project development by TxDOT is completed and TxDOT managed the project. The County paid for construction.
|
Status
|
|
Open to traffic April 2016
|
RM 967 at Ruby Ranch Road Precinct 2
|
Location
|
At Ruby Ranch Road Intersection
|
Description (Completed)
2008 Priority Road Bond Program
|
This project consisted of the widening of the existing RM 967 pavement structure to accommodate a 12-foot left turn lane and shoulders varying from 4 feet (minimum) to 10 feet (maximum). Additional safety improvements included extension of parallel and cross culverts for safety end treatments, replacement of culvert headwalls, and installation of guardrails.
|
Status
|
Open to traffic: August 2013
|
Funding
|
County Road Bonds: $836K
|
FM 150 Center Turn Lane Precinct 1
|
Location
|
FM 150 from Lehman Road to SH 21
|
Description
Partnership Program
Map
|
This project consists of constructing a center turn lane and shoulders within the existing right-of-way for the approximate 4.5-mile corridor. Project development and construction is being conducted and funded by Hays County. Design is underway to add shoulders and a center turn lane to an additional section of FM 150 from New Bridge Road to Waterleaf Blvd. Construction is anticipated to begin in early 2019.
|
Status
|
Construction Start
|
Open to traffic Fall 2017
|
FM 150 West Alignment Precincts 2 and 4
|
Location
|
IH 35 to Arroyo Ranch Blvd./RM 2770
|
Description
Partnership Program
Map
|
This project consists of realigning a section of existing FM 150 from IH 35 to existing FM 150 near Arroyo Ranch Road and would facilitate removing existing FM 150 (Main Street) through the City of Kyle from the State Highway System. County conducted extensive public involvement program to identify corridor for further evaluation. TXDOT has assumed responsibility for preparation of environmental documentation. Hays County will assist in the environmental documentation process by providing schematic design and public involvement services as part of the County's 2016 Road Bond Program. Environmental decision anticipated Summer 2020.
|
|
|
|
|
|
|
|
|
|
|
|
FM 150 West Character Plan Precincts 3 and 4
|
Location
|
Arroyo Ranch Blvd./RM 2770 to RM 12
|
Description
Partnership Program
Map
Improve FM 150
|
This project consists of initiating a corridor study to develop nature, character and potential projects to preserve 4 lanes of capacity and related safety improvements in the east-west corridor in this portion of Hays County in accordance with the County Transportation Plan. The County funded and conducted the corridor study in two Phases and will conduct corridor preservation efforts as appropriate in future phases to be determined.
|
Status
|
Corridor Study
www.improveFM150.com
|
Phase 1 and 2 are complete
|
Lakewood Drive at FM 1626 Precinct 2
|
Location
|
Lakewood Drive from Lewis Lane (CR 307) to FM 1626
|
Description (Complete pending tie-in)
2008 Priority Road Bond Program
|
This project consisted of raising the roadway profile to accommodate a major rain event. This project incorporated safety improvements at the intersection of Lakewood Drive and FM 1626 and replaced the original low water crossing with a bridge.
|
Status
|
Construction completed April 2013; open to traffic July 2015 on completion of FM 1626 North.
|
Funding
|
County Road Bonds: $1.45M
|
FM 1626 North Precinct 2
|
Location
|
RM 967 to Brodie Lane
|
Description
Pass-through Program
Improve 1626
|
This project consists of reconstructing 3.3 miles of existing FM 1626. The existing roadway is a 2-lane rural roadway with limited or no shoulders and several low water areas. The roadway is being reconstructed as a 5-lane rural facility. The project incorporates Context Sensitive design elements developed by the County for the FM 1626 corridor.
|
Status
|
Open to traffic July 2015
FM1626 Before & After:
http://youtu.be/zQhCNGuErF0
|
FM 1626 South (RM 967 to FM 2770) Precinct 2
|
Location
|
Between RM 967 and FM 2770
|
Description
Pass-through Program
Improve 1626.com
|
This project consists of reconstructing 3.2 miles of existing FM 1626. The existing roadway is a 2-lane rural roadway with limited or no shoulders and several low water areas. The roadway will be reconstructed as a 5-lane rural road. The project will incorporate Context Sensitive design elements developed by the County for the FM 1626 corridor.
|
Status
|
Construction Start
|
Construction started November 2016. Estimated completion Summer 2019.
|
RM 12 at Wonder World Drive (FM 3407) Precinct 3
|
Location
|
At Wonder World Drive (FM 3407) Intersection
|
Description (Completed)
2008 Priority Road Bond Program
|
This 1.9-mile project consisted of the widened to 3 lanes (with continuous left turn lanes) and 4-foot shoulders on RM 12 for the connection to the 4-lane divided highway section. Project construction was funded by the City of San Marcos and ROW costs were funded by Hays County.
|
Status
|
Open to traffic: April 2010
|
Funding
|
County Road Bonds: $145K
|
State Funds (ROW Reimbursements): $182K
|
RM 12 at Old Kyle Road Precinct 3
|
Location
|
RM 12 at Old Kyle Road in downtown Wimberley
|
Description (Completed)
2008 Priority Road Bond Program
|
This project consisted of mobility and safety improvements in the downtown Wimberley business district including turn lanes and drainage improvements.
|
Status
|
Open to traffic: May 2013
|
Funding
|
County Road Bonds: $251K
|
Proposition 12 Funding: $440K
|
RM 12 at Hugo Road (CR 214) Precinct 3
|
Location
|
At Hugo Road (CR 214) Intersection
|
Description (Completed)
2008 Priority Road Bond Program
|
This project consisted of constructing one 12-foot right turn lane, one 12-foot left turn lane, two four-foot shoulders with flexible base and hot mix asphalt concrete pavement (HMAC) to match existing roadway. It also incorporated additional safety improvements including the extension of existing cross culverts and re-grading of driveways.
|
Status
|
Open to traffic: July 2012
|
Funding
|
County Road Bonds: $691.5K
|
RM 12 at Sink Creek Precinct 3
|
Location
|
At Sink Creek Bridge
|
Description (Completed)
2008 Priority Road Bond Program
|
This project consisted of the replacement of an existing 200-foot bridge and approaches to accommodate two 12-foot lanes, two 8-foot shoulders and the construction of concrete box culverts as part of the on-going safety improvements along RM 12.
|
Status
|
Open to traffic: July 2012
|
Funding
|
County Road Bonds: $3.25M
|
State Funds (ROW Reimbursement): $447K
|
RM 12 Parkway Development Precinct 3
|
Location
|
RM 12 at Parkway Intersection
|
Description
2008 Priority Road Bond Program
Parkway Plan Info
|
This project consists of preparing a re-evaluation of the environmental document and acquisition of ROW to preserve the corridor for future construction of the proposed 4-lane divided parkway.
|
Status
|
Environmental
|
100%
|
ROW Acquisition
|
90%
|
Funding
|
County Road Bonds: $7.2M (Estimated)
|
RM 12 at Sports Park Drive Precinct 4
|
Location
|
At Sports Park Drive Intersection
|
Description (Completed)
2008 Priority Road Bond Program
|
This project consisted of various safety improvements including a 12-foot left turn lane and four-foot shoulders on RM 12 at Sports Park Drive, extending parallel and cross- culverts, replacement of culvert headwalls and installation of safety end treatments and guardrails.
|
Status
|
Open to traffic: May 2012
|
Funding
|
County Road Bonds: $578.6K
|
Junction of RM 12 at RM 32 Precinct 3
|
Location
|
RM 12 at RM 32 Intersection
|
Description (Completed)
2008 Priority Road Bond Program
|
This project consisted of realigning RM 12 to allow a through movement for RM 12 traffic while creating a T-intersection at RM 32. Project improvements consisted of the construction of two 12-foot lanes, one 14-foot left turn lane, and concrete curb and gutter with flexible base and hot mix asphalt concrete pavement (HMAC) to match existing roadway, along with modifications to cross-culverts and driveways. Similar roadway improvements were incorporated into RM 32.
|
Status
|
Open to traffic: January 2013
|
Funding
|
County Road Bonds: $4.09M
|
State Funds (ROW Reimbursement): $180K
|
RM 12 Safety Improvements Precinct 3
|
Location
|
RM 12/RM 32 to Wonder World Drive
|
Description
Originally a Partnership Program, now funded by the Priority Road Bond Program
|
Originally included in the Partnership Program, this project received funding from other sources. Interim safety “gap” improvements include adding a center turn lane and shoulders at various locations between SH 80 (Hopkins St.) and Saddleridge Drive. The County provided the construction design and TxDOT constructed the improvements. Ultimate improvements (not currently under development) would include a 4-lane divided parkway on 200 to 300 feet of ROW incorporating Context Sensitive Design elements.
|
Status
|
|
1 mile east of Hugo Road to 0.1 mile west of SH 80 – Open to traffic September 2015
Hugo Road to Saddleridge Drive – Open to traffic May 2016
|
RM 2325 (CR 181 to Carney Ln) Precinct 3
|
Location
|
Fischer Store Road (CR 181) to Carney Lane
|
Description (Completed)
2008 Priority Road Bond Program
|
This project consisted of various safety improvements including left and right turn lanes at selected intersections, addition of 4-foot shoulders and improvements to the horizontal alignment and vertical profile in the vicinity of Jacobs Well Elementary to provided increased stopping sight distance. Drainage improvements included the extension of parallel and cross culverts, replacement of culvert headwalls, and installation of safety end treatments and guardrails.
|
Status
|
Open to traffic: January 2013
|
Funding
|
County Road Bonds: $4.74M
|
Lime Kiln Road (CR 225) at Sink Creek Study Precinct 4
|
Location
|
CR 225 at Sink Creek Low Water Crossing
|
Description (Study Completed)
2008 Priority Road Bond Program
|
This project investigated alternatives to the low-water crossing on Lime Kiln Road (CR 225) at Sink Creek by raising the profile of Lime Kiln Road. The proposed alternative roadway would accommodate two 12-foot travel lanes and four-foot shoulders.
Find out more about additions to this project and an informational Open House October 16, 2018.
|
Status
|
Study completed: April 2011
|
Funding
|
County Road Bonds: $222K
|
US 290 West (RM 12 to McGregor Ln) Precinct 4
|
Location
|
US 290 from RM 12 to McGregor Lane
|
Description (Completed)
2008 Priority Road Bond Program
|
This project consisted of the construction of a continuous left-turn lane and improved shoulders along 3.7 miles of US 290 from RM 12 to McGregor Lane.
|
Status
|
Open to traffic: May 2013
|
Funding
|
County Road Bonds: $6.54M
|
US 290 West (Trautwein Rd to Nutty Brown Rd) Precinct 4
|
Location
|
Trautwein Road to Nutty Brown Road
|
Description (Completed)
|
This project constructed a rural cross-section with 4-11’ travel lanes and no shoulders. TxDOT had been adding a center turn lane along many sections of US 290 West from RR 12 to the Hays/Travis County Line. This was the last 2.02-mile section to be improved.
|
Status
|
Open to traffic February 2010
|
RM 1826 at RM 967 Precinct 4
|
Location
|
RM 1826 at RM 967 Intersection
|
Description (Completed)
2008 Priority Road Bond Program
|
This project consisted of widening RM 1826 to accommodate a 12-foot left turn lane and 4-foot shoulders as well as reconstructed the RM 967 approach to include a dedicated right turn lane. This project also included other safety improvements consisting of the installation of safety end treatments by extending parallel and cross culverts, replacing culvert headwalls and installing guardrail.
|
Status
|
Open to traffic: May 2012
|
Funding
|
County Road Bonds: $1.0M
|
RM 1826 at Nutty Brown Road Precinct 4
|
Location
|
RM 1826 at Nutty Brown Road Intersection
|
Description (Completed)
2008 Priority Road Bond Program
|
This project consisted of the construction of a 12-foot left turn lane and 4-foot shoulders on RM 1826 at Nutty Brown Road. The proposed improvements also consisted of reconstructing the Nutty Brown Road (CR 163) approach and drainage structures. Drainage modifications included the extension of parallel and cross culverts, replacement of culvert headwalls, and installation of safety end treatments and guardrail.
|
Status
|
Opened to traffic: September 2013
|
Funding
|
County Road Bonds: $910K
|
Private Developer: $90K
|
RM 1826 at Crystal Hills Drive Precinct 4
|
Location
|
RM 1826 at Crystal Hills Drive Intersection
|
Description (Completed)
2008 Priority Road Bond Program
|
This project consisted of the construction of a 12-foot left turn lane and 4-foot shoulders on RM 1826 at Crystal Hills Drive. Additional safety improvements also included enhancement of the roadway vertical alignment at the Crystal Hills Drive approach, replacement of the low water crossing with an arch bridge and extension of the existing box culvert at Spring Hollow Creek.
|
Status
|
Opened to traffic: July 2013
|
Funding
|
County Road Bonds: $2.07M
|
RM 1826 at Darden Hill Road (CR 162) Precinct 4
|
Location
|
RM 1826 at Darden Hill Road (CR 162) Intersection
|
Description
2008 Priority Road Bond Program
|
This project consists of along RM 1826 and realigning Darden Hill Road to improve the intersection geometry. Safety improvements include widening RM 1826 to incorporate a 12-foot left turn lane and 4-foot shoulders as well as a right turn lane from Darden Hill Road onto RM 1826. Other safety improvements also include the extension of parallel and cross culverts, replacement of headwalls, and installation of safety end treatments and guardrail.
|
Status
|
Environmental
|
95%
|
ROW Acquisition
|
40%
|
Utility Relocation
|
15%
|
Construction Design
|
90%
|
Estimated Construction Start
|
Late 2014
|
Funding
|
County Road Bonds: $1.53M (Estimated)
|
2016 Voter-approved Road Bond Projects
RM 3237 Corridor Safety Improvements Precinct 3
|
Location
|
RM 150 to RM 12
|
Description
Funding Program
|
This project consists of the design and construction of left and right turn lanes at various intersections, shoulder enhancements, and new intersection roundabout at RM 150.
2016 Road Bond Program (Early project development costs through construction design). 80% of construction funding awarded through Capital Area Metropolitan Planning Organization (CAMPO) FY 2019-2022 Transportation Improvement Program process.
|
Status
|
Preliminary Engineering
|
Survey complete.
|
Environmental
|
Not initiated. Anticipated to be a Categorical Exclusion clearance document for elements of the RM 3237 improvement program.
|
ROW Acquisition
|
Additional ROW will be required for this project to accommodate turn lane improvements. Additional ROW will also be required for new roundabout intersection. Not initiated.
|
Utility Relocation
|
Minor utility relocations will likely be identified during final design of the project. Not initiated.
|
Construction Design
|
30% PS&E for the left and right turn lane improvements under development.
|
Construction
|
Estimated to be ready to let in Fall 2019.
|
FM 2001 West Realignment and Expansion Precinct 2
|
Location
|
Sunbright Blvd. to existing FM 2001 alignment
|
Description
Funding Program
|
This project consists of the design and construction of a new horizontal and vertical alignment replacing existing FM 2001 with four-lane divided facility with bike lanes and sidewalks meeting current TxDOT design criteria. Project also includes roadway illumination and the realignment of CR 118 between existing FM 2001 and new FM 2001.
2016 Road Bond Program (Construction design). 80% of construction funding awarded through Capital Area Metropolitan Planning Organization (CAMPO) FY 2019-2022 Transportation Improvement Program process.
Early project development and right-of-way donation program was conducted and funded by Hays County through the Hays County-TxDOT Partnership Program. Construction design and ROW funded through the 2016 Road Bond Program. TxDOT will manage construction.
|
Status
|
Preliminary Engineering
|
Completed.
|
Environmental
|
In process. Environmental clearance anticipated in Fall 2018.
|
ROW Acquisition
|
Majority of ROW acquired through donation. Minimal additional ROW will be required for this project. Not initiated.
|
Utility Relocation
|
Minor utility relocations are anticipated and will be identified during final design to minimize impacts. Initial conflict analysis completed.
|
Construction Design
|
60% completed.
|
Construction
|
Estimated to be ready to let in Spring/Fall 2018.
|
FM 2001 East Realignment and Expansion Precinct 2
|
Location
|
Graef Road to existing FM 2001 southeast of SH 21
|
Description
Funding Program
|
This project consists of constructing two travel lanes (one in each direction) and 10-foot shoulders in the interim time frame of an ultimate four lane divided facility. The existing Rohde Road/SH 21 intersection will be re-aligned and a new FM 2001/SH 21 intersection will be constructed to improve safety, with Rohde Road connecting to SH 21 in the current location.
Early project development and right-of-way donation program was conducted and funded by Hays County through the Hays County-TxDOT Partnership Program. Construction design and ROW funded through the 2016 Road Bond Program. TxDOT will fund and manage construction.
2016 Road Bond Program (Construction design, ROW acquisition & utility relocation; Phase 1 construction funded by TxDOT).
|
Status
|
Preliminary Engineering
|
Completed.
|
Environmental
|
In process. Environmental clearance anticipated in Fall 2018.
|
ROW Acquisition
|
50% of ROW acquired through donation. Acquisition of remaining 50% of required ROW not initiated.
|
Utility Relocation
|
Not initiated.
|
Construction Design
|
Underway.
|
Construction
|
Estimated to be ready to let in Spring/Summer 2019.
|
RM 967 Safety Improvements Precinct 2
|
Location
|
FM 1626 to Oak Forest Drive
|
Description
Funding Program
|
This project consists of the evaluation, design and reconstruction of a widened RM 967 with center turn lane, shoulder enhancements, and improved geometry to meet existing TxDOT design criteria. Project also includes left and right
turn lanes and signal modifications at Buda Sportsplex Drive, new turn lanes for Hays Consolidated ISD Hays High School south of Carpenter Hill Elementary School. Additional developer participation may be incorporated for additional right turn lanes.
2016 Road Bond Program (Early project development costs through construction design). 80% of construction funding awarded through Capital Area Metropolitan Planning Organization (CAMPO) FY 2019-2022 Transportation Improvement Program process.
|
Status
|
Preliminary Engineering
|
Completed.
|
Environmental
|
In process. Anticipated to be a Categorical Exclusion clearance document.
|
ROW Acquisition
|
Minor ROW acquisition from Hays Consolidated ISD is anticipated to accommodate the widened roadway typical section and to improve vertical alignment. Additional ROW may be needed for developer-related right turn lanes and vertical alignment adjustment. Not initiated.
|
Utility Relocation
|
Minor utility relocations are anticipated and will be identified during design to minimize impacts. Not initiated.
|
Construction Design
|
30% completed.
|
Construction
|
Estimated to be ready to let in Spring
2019.
|
RM 150 West Alignment Precincts 2 and 4
|
Location
|
Interstate 35 at Yarrington Road to RM 150 west of City of Kyle
|
Description
Funding Program
|
This project consists of realigning a section of existing FM 150 from IH 35 to existing FM 150 near Arroyo Ranch Road and would facilitate removing existing FM 150 (Main Street) through the City of Kyle from the State Highway System. County conducted extensive public involvement program to identify corridor for further evaluation. TxDOT has assumed funding and management responsibility for preparation of environmental documentation.
2016 Road Bond Program (funding through the Program only for schematic preparation and public involvement during the environmental clearance process, ROW acquisition and utility relocation).
|
Status
|
Preliminary Engineering
|
Initial alignments presented at August 2, 2018 public meeting.
|
Environmental
|
First public meeting of environmental documentation process held on August 2, 2018. Second public meeting anticipated in October 2018.
|
ROW Acquisition
|
Not initiated.
|
Utility Relocation
|
Not initiated.
|
Construction Design
|
To be determined.
|
Construction
|
To be determined.
|
FM 110 Overpass at SH 123 Precinct 1
|
Location
|
FM 110 at SH 123 intersection
|
Description
Funding Program
|
Element of overall FM 110 Corridor from I-35 at McCarty to I-35 at Yarrington Road project. This project consists of the design of a new overpass to grade separate the FM 110 at SH 123 intersection in accordance with the approved TxDOT schematic and approved EA.
2016 Road Bond Program (Construction design). 80% of construction funding awarded through Capital Area Metropolitan Planning Organization (CAMPO) FY 2019-2022 Transportation Improvement Program process.
|
Status
|
Preliminary Engineering
|
Completed.
|
Environmental
|
Completed.
|
ROW Acquisition
|
Completed.
|
Utility Relocation
|
Completed.
|
Construction Design
|
30% completed.
|
Construction
|
Estimated to be let in Summer 2019.
|
FM 621 Corridor Safety Improvements Precinct 1
|
Location
|
Old Bastrop Highway (CR 266) to De Zavala Drive
|
Description
Funding Program
|
This project consists of the evaluation, design and construction of left turn improvements at several intersections along the corridor, shoulder enhancements and improved geometry to meet existing TxDOT design criteria. Project also includes intersection improvements (including left turn lanes) and signal modifications at Old Bastrop Highway.
2016 Road Bond Program (Early project development costs through construction design. 80% of construction funding awarded through Capital Area Metropolitan Planning Organization (CAMPO) FY 2019-2022 Transportation Improvement Program process.
|
Status
|
Preliminary Engineering
|
Completed.
|
Environmental
|
In process. Anticipated to be a Categorical Exclusion clearance document.
|
ROW Acquisition
|
Not initiated. Minor ROW acquisition is anticipated to accommodate the widened roadway typical section and to improve horizontal alignment improvements. Not initiated.
|
Utility Relocation
|
To be determined.
|
Construction Design
|
30% under development.
|
Construction
|
Estimated that this project will be ready to let in Spring 2019.
|
US 290 West Safety Improvements Precinct 4
|
Location
|
At Trautwein Road, Holder Lane intersections
|
Description
Funding Program
|
At Trautwein Road, the project consists of the evaluation, design and construction of intersection improvements including installation of decleration and right turn lanes, as well as improved vertical geometry.. At Holder Lane, the project consists of evaluation, design and construction of a dedicated right turn lane and shoulder improvements.
2016 Road Bond Program (Early project development costs through construction design for both locations; local cost-share (20%) for construction for improvements at Trautwein Road; 100% construction for Holder Lane). 80% of construction funding awarded through Capital Area Metropolitan Planning Organization (CAMPO) FY 2019-2022 Transportation Improvement Program process for improvements at Trautwein Road.
|
Status
|
Preliminary Engineering
|
Completed.
|
Environmental
|
In process. Anticipated to be a Categorical Exclusion Checklist clearance document.
|
ROW Acquisition
|
Not required for Trautwein Road.; ROW required for Holder Lane. Not initiated.
|
Utility Relocation
|
Minor utility relocations are anticipated and will be identified during design to minimize impacts. Not initiated.
|
Construction Design
|
30% completed.
|
Construction
|
Estimated that this project will be ready to let in Spring 2019 (Trautwein Road Intersection). Anticipated that Trautwein Road improvements will be let and managed by TxDOT and that Holder Lane improvements will be let and managed by Hays County.
|
RM 150/RM 12 Intersection Improvements Precinct 4
|
Location
|
RM 150 at RM 12
|
Description
Funding Program
|
This project would consist of the evaluation, design and construction of intersection improvements at RM 150 and RM 12.
Transportation Department funding early project development costs.
|
Status
|
Preliminary Engineering
|
Underway.
|
Environmental
|
Underway.
|
ROW Acquisition
|
Not initiated.
|
Utility Relocation
|
Not initiated.
|
Construction Design
|
Not initiated.
|
Construction
|
To be determined.
|
RM 12/RM 3237 Intersection Improvements Precinct 3
|
Location
|
RM 12 at RM 3237
|
Description
Funding Program
|
This project would consist of the evaluation, design and construction of intersection improvements at RM 12 and RM 3237.
2016 Road Bond Program (Early project development costs through construction design); $320,000.00 in project funding awarded through Capital Area Metropolitan Planning Organization (CAMPO) Transportation Improvement Program process and will be used toward construction.
|
Status
|
Preliminary Engineering
|
Completed.
|
Environmental
|
Underway.
|
ROW Acquisition
|
Minor ROW will be required. Not initiated.
|
Utility Relocation
|
Not initiated.
|
Construction Design
|
Not initiated.
|
Construction
|
To be determined.
|
Winters Mill Parkway Intersection Improvements – Precinct 3
|
Location
|
Winters Mill Parkway at RM 12 and RM 3237
|
Description
Funding Program
|
This project consists of the design and construction of right turn lanes at RM 12 and RM 3237 and other intersection improvements at each intersection.
2016 Road Bond Program (Construction only).
|
Status
|
Preliminary Engineering
|
Complete
|
Environmental
|
In process. Anticipated to be a Categorical Exclusion Checklist clearance document.
|
ROW Acquisition
|
Not initiated.
|
Utility Relocation
|
Not initiated.
|
Construction Design
|
90% completed.
|
Construction
|
To be determined.
|
SH 80 Intersection Improvements
|
Location
|
SH 80 at Old Bastrop Highway (CR 266) and Military Drive
|
Description
Funding Program
|
This project consists of the design and construction of safety improvements throughout the corridor, including shoulder improvements and left turn lanes and other intersection improvements at Old Bastrop Highway (CR 266) and Military Drive.
2016 Road Bond Program (Early project development costs through construction design). $1.2 million of construction funding awarded through Capital Area Metropolitan Planning Organization (CAMPO) Transportation Improvement Program process.
only for improvements at SH 80 at Old Bastrop Highway (CR 266).
|
Status
|
Preliminary Engineering
|
Underway.
|
Environmental
|
Not initiated.
|
ROW Acquisition
|
Not initiated.
|
Utility Relocation
|
Not initiated.
|
Construction Design
|
Not initiated.
|
Construction
|
To be determined.
|
Lime Kiln Road Safety Bridge Improvements Precincts 3 and 4
|
Location
|
Post Road to Hilliard Road
|
Description
Funding Program
|
The project consists of the design and construction of a new horizontal and vertical alignment replacing two
existing low water crossings and improving horizontal and vertical alignments while minimizing property impacts and impacts to the floodplain. The project also aligns the offset intersections with Windermere Road through intersection improvements.
2016 Road Bond Program (ROW acquisition and local share of construction). 80% of construction funding awarded through Capital Area Metropolitan Planning Organization (CAMPO) FY 2019-2022 Transportation Improvement Program process.
|
Status
|
Preliminary Engineering
|
Completed.
|
Environmental
|
County due diligence in process; environmental clearance anticipated in Fall 2018.
|
ROW Acquisition
|
Not initiated.
|
Utility Relocation
|
Minor utility relocations are anticipated and are being identified during final design to minimize impacts.
|
Construction Design
|
90%
|
Construction
|
Estimated that this project will be ready to let in Spring 2019.
|
Sawyer Ranch Road Shared Use Path Precinct 4
|
Location
|
Meadow Creek Drive to Belterra Drive
|
Description
Funding Program
|
The project consists of the evaluation, design and construction of shared use path improvements along Sawyer Ranch Road between the Highpointe, Meadow Creek and Belterra subdivisions and
connecting to Sycamore Springs schools in the middle of the project limits.
2016 Road Bond Program (Early project development costs through construction design. ROW acquisition and construction).
|
Status
|
Preliminary Engineering
|
Completed.
|
Environmental
|
County due diligence complete.
|
ROW Acquisition
|
Easement from Dripping Springs ISD acquired.
|
Utility Relocation
|
Minor utility relocations are included in construction contract.
|
Construction Design
|
Complete.
|
Construction
|
Fall 2018.
|
Hillside Terrace Precinct 2
|
Location
|
I-35 to FM 2001
|
Description
Funding Program
|
This project consists of Phase 1 efforts to include sufficient preliminary engineering to identify phased program of maintenance, interim and ultimate safety and mobility improvements.
Phase 2 would include environmental, ROW needs identification and construction design of identified priority projects.
2016 Road Bond Program (Construction Design & ROW Acquisition).
|
Status
|
Preliminary Engineering
|
Not initiated. Design engineer selected.
|
Environmental
|
Not initiated
|
ROW Acquisition
|
Not initiated
|
Utility Relocation
|
Not initiated
|
Construction Design
|
Not initiated
|
Construction
|
To be determined.
|
Low Water Crossings Precincts 1 and 2
|
Locations
|
Phase 1 preliminary engineering studies were conducted for 15 low water crossings in Precincts 1 and 2. Phase 2 will include environmental clearance, construction design, right of way acquisition and construction of the following 7 the low water crossings studied in Phase 1:
- Bunton Lane Location 1
- Bunton Lane Location 2
- Bunton Lane Location 3
- Francis Harris Lane
- S. Turnersville Road
- Grist Mill Road
- Cotton Gin Road
Additionally, as part of Phase 1, full construction design was completed for the Chaparral Road at Bear Creek crossing.
|
Description
Funding Program
|
Design and construction of approaches and bridge improvements.
2016 Road Bond Program (Early project development costs through construction design).
|
Status (Phase 2 – 7 Low Water Crossings)
|
Preliminary Engineering
|
Complete
|
Environmental
|
Underway
|
ROW Acquisition
|
Underway
|
Utility Relocation
|
Underway
|
Construction Design
|
Underway
|
Construction
|
To be determined
|
Low Water Crossings Precincts 3 and 4
|
Locations
|
- Sycamore Creek
- Bear Creek
|
Description
Funding Program
|
Design and construction of approaches and bridge improvements at various low water crossings.
2016 Road Bond Program (Early project development costs through construction design).
|
Status
|
Preliminary Engineering
|
Complete
|
Environmental
|
Underway
|
ROW Acquisition
|
Preliminary acquisition efforts underway.
|
Utility Relocation
|
To be determined.
|
Construction Design
|
Underway.
|
Construction
|
To be determined.
|
Old Bastrop Highway (CR 266) Precinct 1
|
Location
|
Rattler Road to Centerpoint Road
|
Description
Funding Program
|
This project consists of the widening and reconstruction of existing Old Bastrop Highway (CR 266) to provide for two 12-foot lanes and 8 to 10-foot shoulders on each side.
2016 Road Bond Program (Early project development costs through construction).
|
Status
|
Preliminary Engineering
|
Completed.
|
Environmental
|
County due diligence in process.
|
ROW Acquisition
|
To be determined.
|
Utility Relocation
|
To be determined.
|
Construction Design
|
30% completed.
|
Construction
|
To be determined.
|
Fischer Store Road Intersection Improvements
|
Location
|
Fischer Store Road at RM 2325
|
Description
Funding Program
|
Design and construction of turn lane improvements at the Fischer Store Road/RM 2325 intersection.
2016 Road Bond Program (construction only).
|
Status
|
Preliminary Engineering
|
Complete.
|
Environmental
|
Underway
|
ROW Acquisition
|
Underway.
|
Utility Relocation
|
Coordination continuing.
|
Construction Design
|
95%
|
Construction
|
To be determined.
|
Darden Hill Widening and Turn Lanes
|
Location
|
FM 1826 to Sawyer Ranch Road
|
Description
Funding Program
|
Design and construction of widening of travel lanes, and shoulder improvements and turn lanes at to be determined locations.
2016 Road Bond Program (Early project development costs through construction design and ROW acquisition).
|
Status
|
Preliminary Engineering
|
Not initiated. Design engineer selected.
|
Environmental
|
To be determined.
|
ROW Acquisition
|
To be determined.
|
Utility Relocation
|
To be determined.
|
Construction Design
|
Not initiated.
|
Construction
|
To be determined.
|