On Friday September 27, 2013, Hays County officials joined the Texas Department of Transportation, with State Representative Jason Isaac in attendance, in hosting a ribbon-cutting ceremony to mark the completion of work on RM 150, as well as frontage road improvements on I-35, in Kyle.  The $3.5 million project straightened RM 150 to enhance operations at the intersection of I-35 and improved access to FM 150 from the east side of I-35.  Work on the realignment project began in September 2012 by Capital Excavation Company, of Buda.  In addition, a $6.3 million I-35 frontage road reconstruction and ramp revision project was completed.  Crews constructed a southbound frontage road at RM 150 and converted the I-35 frontage roads to one-way between FM 1626 and RM 150.  Work on the frontage road project began in August 2012.  The project contractor was Hunter Industries, of Hunter Texas.

Wednesday, November 13, 2013 10:08:00 AM Categories: Press Releases